Capacity (kW):
253.60
Country :
England
Town/County :
Shropshire
Developer :
farmpoint ltd
Commission Date :
21st Jul 2011
Connection Type :
Embedded in Distribution System
Last Updated :
6th Feb 2016

Comberton Poultry Farm
Park Lane
Woofferton
Ludlow
Shropshire
SY8 4AJ
England

To calculate the capacity factor for PV, we calculate how many hours (on average) the sun will be more than 12.5 degrees above the horizon (at the calculated location) and use that figure to calculate the potential output.

Month Daily Average Sun Hours Potential Capacity (kWH)
January 5.14 40,408.62
February 7.33 52,048.86
March 9.57 75,235.51
April 11.61 88,328.88
May 13.19 103,694.50
June 13.95 106,131.60
July 13.57 106,681.91
August 12.20 95,911.52
September 10.32 78,514.56
October 8.12 63,836.19
November 5.79 44,050.32
December 4.26 33,490.42

NB potentials shown assume a non leap year and are only meant for comparison. Actual values used are calculated on actual number of days in month.

Technology Group :
Photovoltaic
Generation Type :
General
Scheme Accreditation No. Date
REGO G04553PVEN 22 Jul 2011

This station is not connected directly to the grid.

Average Capacity Factors

Sep 2015

31.84%

Dec 2014 to Sep 2015

28.53%

Recent Months

Period Theoretical Capacity (MWh) Reported Output (MWh) Capacity Factor (%)
Sep 2015 78.51 25.00 31.84
Aug 2015 95.91 26.00 27.11
Jul 2015 106.68 33.00 30.93

View full output data »

These figures only represent a best estimate.

Total Income

Sep 2015 to Nov 2015

£ 1,180.75

Dec 2014 to Nov 2015

£ 10,970.13

Recent Months

Period Estimated Income (£)
Sep 2015 1,180.75

View full finance data »

  • Capitalisation has not been changed from that used by the underlying data source.
  • The capacity figure shown is from Ofgem.
  • If there is no information shown for a period it is due to there being no data available to display.